Hi Alyssa, The job takes 9 employees 15 days so the amount of work required is 9 × 15 = 135 employee-days. If you have 3 additional employees that gives 12 employees so how many days would it take for 12 employees to complete 135 employee-days of work? Penny | ||||||||||||
|
||||||||||||